Hinjewadi Electric Supply Restored After 72 Hours: What Caused the Power Outage?

By Priya Agarwal

Published on:

Hinjewadi Electric Supply Restored After 72 Hours What Caused the Power Outage

Hinjewadi Electric Supply Restored After 72 Hours – What Happened?

For three days, many areas in and around Hinjewadi faced major problems due to a power cut. Finally, after 72 hours, electricity supply was brought back to normal, giving much-needed relief to residents and people working in the IT sector.

What caused the Hinjewadi Electric Supply issue?

The issue started on Sunday, June 6, around 2 PM. A fault occurred in the 220 kV underground power line that connects Infosys and Pegasus substations near Phase 2 in Hinjewadi. This failure stopped electricity supply not only in Hinjewadi but also in nearby areas like Marunji, Maan, and parts of MIDC.

The repair work began quickly, but due to the scale of the damage, it took three full days to fix. On Wednesday, June 9, at 12:40 PM, Maharashtra State Transmission Company Limited (Mahapareshan) completed the repair, and the power was restored to all affected zones.

How many people and companies were affected?

The breakdown had a big impact. Over 12,000 low-voltage users and 91 high-voltage users were affected. This included:

  • 25 feeder lines at 22kV voltage
  • Large companies like Infosys and Nextra
  • Thousands of local homes and businesses

Due to this failure, many IT companies had to shut down operations temporarily, affecting productivity and causing losses.

Type of UserNumber Affected
Low-voltage usersAround 12,000 homes
High-voltage users91 companies
Major clientsInfosys, Nextra
Feeder lines25 lines disrupted

Why did it take so long to fix?

Fixing such a large underground power line isn’t simple. The team had to locate the fault, dig in the right areas, and make sure everything was safe before restoring power. According to the chief engineer, Sunil Kakade, this was not a small breakdown. The damage was major, and rerouting electricity from other sources was very difficult.

Yet, thanks to the efforts of technicians and engineers, the problem was solved, and power was brought back safely.

Timeline of Events

Date & TimeEvent
Sunday, June 6, 11 AMPower supply stopped for maintenance
Sunday, June 6, 2:10 PMFault occurred in the 220 kV underground line
Monday, June 7Partial supply restored to some residential users
Wednesday, June 9, 12:40 PMComplete repair done; all supply restored

Areas Affected by the Hinjewadi Electric Supply Failure

Many parts of Hinjewadi and nearby localities saw full or partial blackouts. A few of the areas hit the hardest were:

  • Hinjewadi Phase 1, 2, and 3
  • Marunji
  • Maan village
  • MIDC industrial areas
  • Surrounding residential societies
  • Metro station area near Phase 2

People living in these areas had to manage without electricity for long hours. Some had power for a few hours through alternate arrangements, but it wasn’t stable.

Impact on Hinjewadi IT Park

Hinjewadi IT Park is one of the biggest tech hubs in India. It houses many top national and international IT companies. The blackout caused huge disruption.

Work in many companies came to a stop. Data centers, servers, and communication systems were down. Backup power wasn’t enough in many offices, and the overall work output was hit badly.

This blackout raised many questions about the quality of infrastructure in a region that is supposed to be a global IT destination.

Government Action After the Power Failure

The scale of this failure pushed the government to act. A high-level meeting was held with top leaders including Deputy CM Ajit Pawar and senior officials.

Key steps announced:

  • An action plan to fix infrastructure in Hinjewadi IT Park
  • Completion of basic civic work by December
  • Fast-tracking metro construction
  • Focus on solving pothole problems
  • Appointment of a coordination officer between gram panchayat, MIDC, and PMC
  • Formation of a consulting committee to study and solve the water logging issue

These steps are meant to improve living and working conditions in Hinjewadi and avoid such incidents in the future.

What Mahapareshan Said

According to officials from Mahapareshan (Maharashtra State Transmission Company), this was a major fault in one of the most critical high-voltage underground lines. Shifting the power load to other lines was very hard.

Despite that, the engineers worked around the clock to fix the problem. Once repairs were complete, all affected users — homes, industries, and IT companies — got normal supply.

Was this planned?

Interestingly, Mahapareshan had announced a short power shutdown for routine maintenance on Sunday morning from 11 AM to 1 PM. This was published in local newspapers.

But the real issue happened after the maintenance — around 2:10 PM — when the cable failed unexpectedly. So, while people expected a short outage, they ended up facing three days without proper electricity.

Why is Hinjewadi’s Electric Supply so important?

Hinjewadi is not just a residential area. It’s a key economic zone for Pune and Maharashtra. It contributes significantly to the IT industry, employment, and business activities. Any long power outage here causes:

  • Loss of work hours
  • Production delays in industries
  • Communication problems in IT services
  • Inconvenience to thousands of residents

Reliable power supply in such areas is not just necessary — it’s critical.

Hinjewadi Electric Supply Restored After 72 Hours What Caused the Power Outage

What can be done to avoid this again?

Power failures like this can cause massive losses. Here’s what experts suggest:

1. Regular Testing of High-Voltage Lines

Periodic checks help catch weak spots early.

2. Better Backup Plans

IT parks and industries should have powerful backup generators.

3. Smart Grid Systems

Using technology to reroute power instantly during faults.

4. Faster Communication

Real-time updates via SMS or app can help people prepare better.

5. Government Monitoring

Active monitoring of important infrastructure in key zones like Hinjewadi.

What people in Hinjewadi are saying

Many residents of Hinjewadi shared that they were frustrated during the blackout. Mobile towers didn’t work well, water pumps were shut, and even traffic signals stopped functioning in some areas.

But once the power returned on Wednesday, people were relieved. Most said that after power was restored at noon, it remained stable. Many appreciated the efforts of the technical team but also demanded stronger systems in the future.

Frequently Asked Questions (FAQ)

Q1: What caused the Hinjewadi electric supply breakdown?

A fault in the 220 kV underground high-voltage line between Infosys and Pegasus substations.

Q2: How long did the power outage last?

It lasted for about 72 hours, from Sunday afternoon to Wednesday noon.

Q3: Who was affected by this outage?

Over 12,000 residential users and 91 high-voltage industrial and IT users in Hinjewadi and nearby areas.

Q4: What action has the government taken?

The state government has created an action plan to fix basic infrastructure, speed up metro work, and coordinate between departments.

Q5: Is the Hinjewadi electric supply stable now?

Yes, as of June 9 afternoon, full supply was restored and has remained stable since then.

The Hinjewadi Electric Supply issue has shown how important infrastructure maintenance is, especially in critical zones like tech parks. While the problem was eventually solved, it caused serious inconvenience.

Going forward, better planning, regular checks, and quicker communication can help avoid such situations. With the government’s new action plan, people hope for a more reliable electric supply in Hinjewadi.

For now, the power is back. But the focus must stay on long-term solutions to keep Hinjewadi running — always.